General SummaryThis case is from a collection containing the full text of over 16,000 Supreme Court cases from 1793 to the present. The body of Supreme Court decisions are, effectively, the final interpretation of the Constitution. Only an amendment to the Constitution can permanently overturn an interpretation and this has happened only four times in American history.
United States v. American Surety Co., 322 U.S. 96 (1944)
United States v. American Surety Co. No. 381 Argued March 27, 28, 1944 Decided April 24, 1944 322 U.S. 96
CERTIORARI TO THE CIRCUIT COURT OF APPEALS
FOR THE NINTH CIRCUIT
Syllabus
1. Under the Government construction contract here involved, the Government was not entitled to recover liquidated damages for delay in completion where, though subsequently to the specified completion date, the Government terminated the contractor’s right to proceed. P. 100.
2. A Government construction contract may validly provide for liquidated damages in limited situations only. Act of June 6, 1902, § 21. P. 101.
136 F.2d 437 affirmed.
Certiorari, 320 U.S. 729, to review a judgment which reversed in part a Judgment for the United States in a suit upon a construction contract, 44 F.Supp. 871.
Contents:
Chicago:
U.S. Supreme Court, "Syllabus," United States v. American Surety Co., 322 U.S. 96 (1944) in 322 U.S. 96 Original Sources, accessed July 1, 2025, http://www.originalsources.com/Document.aspx?DocID=B9G7MRMCVWW67N7.
MLA:
U.S. Supreme Court. "Syllabus." United States v. American Surety Co., 322 U.S. 96 (1944), in 322 U.S. 96, Original Sources. 1 Jul. 2025. http://www.originalsources.com/Document.aspx?DocID=B9G7MRMCVWW67N7.
Harvard:
U.S. Supreme Court, 'Syllabus' in United States v. American Surety Co., 322 U.S. 96 (1944). cited in 1944, 322 U.S. 96. Original Sources, retrieved 1 July 2025, from http://www.originalsources.com/Document.aspx?DocID=B9G7MRMCVWW67N7.
|